Project B: Tollington Park Baptist Church, London N4

 

The former church comprised three buildings - one late 19th century, one early 20th century, both linked by a hall built in the early 1970's. All three buildings had maintenance problems associated with age; as a result not all of the extensive footprint was being utilised.

 

All three buildings were demolished and a plot of the church's land was sold to a housing association in order to generate funds for a rebuild. In addition to recovering 75% of the floor space of the former church buildings (as a result of building on different levels), the church also acquired a 3 bedroom flat.

 

Simply Churches Role

* Employer's Agent

Benefits of the project

* more efficient use of space

* running costs reduced

* welcoming glazed entrance

* circulation  

New accommodation

* glazed entrance area serving as an access point to the rest of the building

* main worship area seating 150, with baptismal pool, raised dias

* three further meeting rooms

* kitchen & toilets (including disabled) 

* integral lift (serving both kitchen and foyer)

Project challenges

* corner site

* financing (sale of land)

  * temporary alternative accommodation  

Procurement method

* design & build

Statistics

* completed July 2000

  * contract value £650,000